Most BIM coordination meetings in GCC villa projects cover the same checklist.
MEP clashes. Structural penetrations. Façade interfaces.
The flat roof window is not on the checklist.
Not because it’s unimportant — but because it was specified by a different consultant, at a different stage, on a different drawing set.
The structural engineer drew the slab. The architect specified the skylight opening. The BIM coordinator received neither.
So the model goes to construction with a solid slab where the opening should be.
The clash is discovered at week 34 — when the concrete is already poured.
At that point, the options are: — Core-drill through post-tensioned slab: structural risk + engineer’s approval + 3-week delay. — Relocate the opening: affects the room below, the blind specification, and the EN 17037 daylight calculation. — Remove the skylight from the scope: the room loses its only source of natural light.
None of these were in the programme. All of them were avoidable.
The flat roof window opening needs to be in the structural BIM model from SD stage — not added as a coordination note at DD, and not discovered during construction.
It is a structural penetration. It needs to be treated like one.
Project directors: at what stage does the skylight opening appear in your BIM coordination model?