The best project managers in GCC construction plan the roof differently.
They don’t add the flat roof window at week 18, when the structural drawings are done. They don’t discover the lead time at week 22, when the subcontractor places the order. They don’t find out the opening doesn’t fit at week 34, when the slab is already poured.
They put the skylight in the programme at week 2.
Not because it’s the most complex item on scope. Because it’s the one that locks everything else.
The upstand dimension defines the structural penetration. The structural penetration defines the slab reinforcement. The slab reinforcement defines what can be changed — and what can’t.
A flat roof window with a 6-week lead time, specified at SD stage and ordered at the start of procurement, arrives on site before the concrete is poured. The opening is pre-coordinated. The upstand is in the structural drawings. The blind is on the M/E schedule.
A flat roof window discovered at construction stage arrives after the slab is poured. The options that remain — core drilling, repositioning, scope removal — all cost more than the window itself.
The difference between these two outcomes is not the product. It’s the week the project manager put it in the programme.
The teams that get this right treat the skylight like the structural element it is — not like a finishing item that can be slotted in at the end.
At what stage does your team include the flat roof window in the programme of works — concept design, or after the structural package is awarded?
Shams Daylighting Solutions (UAE) www.shamsds.ae
Learn more about VELUX Flat Roof Windows — or contact our team at hello@shamsds.ae.