The skylight line item tends to appear in the procurement schedule later than it should.
On most GCC flat roof projects, it goes in after the structural package is issued — sometimes after the slab is poured. By that point, the opening is fixed, the waterproofing contractor has a date, and the ceiling finishes are already sequenced. What isn’t fixed is the window configuration, the upstand height, or the lead time.
A VELUX flat roof window is not a stock item. The upstand, the glazing unit and the motorised mechanism are ordered as a configured system. The procurement team needs a confirmed specification to place the order, and the specification needs a confirmed opening size. That chain works well when the skylight enters the programme at design freeze. It creates pressure when it enters at procurement close.
Project managers and quantity surveyors who build the skylight into the programme early — alongside the structural and MEP packages — tend to avoid that pressure. Not because they have more time, but because they have the right information at the right stage.
For lead times and configuration support on GCC projects, contact us at hello@shamsds.ae or visit our flat roof window range at shamsds.ae/new-generation/.