There’s a pattern I’ve seen consistently across GCC construction projects that deliver on time and within spec: the procurement team didn’t write “skylight” in the tender document. They wrote performance criteria.
Specifically:
- Minimum SHGC: 0.12 (EN 13363-1)
- Minimum light transmittance: 60%
- Thermal transmittance (U-value): ≤1.4 W/m²K
- Compliance: EN 17037 daylighting standard
- Ventilation: operable, with rain sensor
That’s not over-engineering. That’s protecting the project from substitutions that technically comply but don’t perform in the GCC climate.
What Happens When the Spec Names a Brand Instead of a Standard
When a tender document names a brand rather than a performance standard, three things tend to follow:
- Substitutions arrive at site that technically “comply” — but don’t perform under GCC summer conditions.
- The consultant spends weeks reviewing alternatives nobody asked for.
- The developer ends up with a roof that works on paper and fails in practice.
The procurement managers who avoid this don’t do it by luck. They lock the performance criteria before the tender goes out — not after the slab is poured.
The Specification Window Is Narrower Than Most Programmes Allow
In GCC villa and commercial projects, the window to influence the roof specification closes earlier than most teams expect. By the time structural drawings are issued, the slab position, opening dimensions and load assumptions are already fixed. Changing the specification after that point carries real cost — in time, in redesign, and in contractor negotiations.
The best procurement teams build the performance criteria into the tender package from concept stage. That means the consultant, the contractor and the supplier are all aligned before the first RFI lands.
How Shams Daylighting Supports the Specification Process
At Shams Daylighting Solutions, we work with procurement teams, project managers and consultants across UAE and KSA to align flat roof window specifications to GCC performance requirements — before the tender stage, not after.
Our range of VELUX flat roof windows (new generation) and first-generation systems are specified to EN 17037 and EN 13363-1 standards, with full technical documentation available for submittal packages.
If your team is preparing a tender for a GCC project and wants to align on performance criteria, we’re happy to support — no obligation.